If you own or are buying a townhouse or condo in Langley, South Surrey or White Rock, there is a strata deadline six weeks out that most owners have not heard of. By December 31, 2026, every strata corporation in this region with five or more strata lots has to have an electrical planning report. Once it has one, or once the deadline passes, the rules for an owner asking to install an EV charger change in the owner's favour.
Why the deadline applies here
The province set two dates. Stratas in the Metro Vancouver Regional District, the Fraser Valley Regional District and the Capital Regional District have until December 31, 2026. The rest of the province has until December 31, 2028. The Township of Langley, the City of Langley, Surrey and White Rock are all member jurisdictions of Metro Vancouver, so the 2026 date is the one that applies to every complex in this area.
New stratas get five years from the deposit of the strata plan. Phased developments have their own timeline in the regulation. Stratas of four or fewer lots do not need a report.
What an electrical planning report is
Almost every strata, townhouse complexes and bare land stratas included, has a fixed amount of electrical capacity. Adding more from the utility can be expensive. The report is meant to show how much is left before anyone adds chargers or heat pumps. Under the Strata Property Regulation it has to cover:
- The current capacity of the strata's electrical system.
- The existing demands on it.
- An estimate of peak demand and spare capacity.
- An estimate of the capacity needed for future demands, such as EV charging and heat pumps.
- Recommendations for managing and reducing demand. The province's example is switching to LED lighting.
The province is clear that this is an overview, not an engineering design. It cannot be used to approve a specific installation. Anyone adding load still needs a qualified professional to confirm the capacity. It is also not the same as an EV Ready Plan, which works out what it would take to put charging in every parking stall. Some providers do both.
There is a shorter version for the rare strata where every lot is connected straight to the utility with no shared electrical system, as can happen in a bare land strata of detached homes. The provider has to confirm that and issue a shorter report. The province notes that each house getting its own BC Hydro bill does not prove it.
Who can write it and how it is paid for
Only designated professionals can prepare the report. For any building that means a professional engineer, a professional licensee engineering, an applied science technologist or a certified technician. For Part 9 buildings under the BC Building Code, which the province describes as three storeys or less and no more than 600 square metres in footprint, a journeyperson construction or industrial electrician can also do it. The province gives condo towers and mid rise apartment blocks as examples of Part 3. The strata can confirm which with the local government.
Like a depreciation report, the cost can come from the operating fund, if it is in the budget passed at the AGM, or from the contingency reserve fund by a majority vote at a general meeting. How the reserve fund works is covered in strata depreciation reports in BC.
What changes for an owner who wants a charger
Once the strata has its report, or once December 31, 2026 passes without one, a set process applies to an owner's request to install EV charging. The key points from the province's guidance:
- The request has a set form. It must include the owner's contact information and strata lot number, a description of the charging equipment, where it would be used, the name and contact information of a qualified contractor, the contractor's description of the work, and the contractor's estimate of cost and time.
- Council has three months to decide.
- It cannot unreasonably refuse a request made properly. It can say no if, for example, there is not enough electrical capacity. That is where the report matters.
- The owner can be made to pay. Council can require the owner to cover the installation cost, and can set reasonable conditions in writing: approval of the equipment, contractors and materials, payment in advance, and an agreement to modify or replace the installation if the strata later puts in charging for more owners.
- A parking stall can come with it. If the stall is common property and the owner paid for the installation, the strata can grant exclusive use of that stall for up to five years.
- Electricity can be billed back. The strata can charge a reasonable user fee based on consumption, if it is authorized in a bylaw or in a rule ratified by majority vote at a general meeting.
A strata of four or fewer lots does not need a report, but the same approval process applies to it from December 31, 2026.
Lower vote thresholds for the strata itself
Separately, since December 6, 2023, several EV decisions that used to need a three quarter vote now need only a majority. That covers spending from the reserve fund on EV charging or on a report about it, a significant change to common property for EV charging, and buying or selling strata owned charging equipment. A special levy for EV charging still needs a three quarter vote.
What buyers should look for in the strata documents
The electrical planning report is a permanent strata record and has to be disclosed on the Form B Information Certificate when an owner or a prospective buyer asks for it. If you are buying in a complex of five or more units, ask for:
- The report itself, or the date it is booked. After December 31, 2026, a strata without one is behind.
- The spare capacity figure. If you drive an EV or plan to, this tells you whether a charger is realistic.
- Any EV Ready Plan, and the minutes about it. Shared charging projects often come with a levy or a fee.
- Bylaws or rules on charging fees. What you would pay for the electricity.
- Heat pump plans. The report weighs EV charging against heating and cooling. If capacity is tight, owners may be competing for it.
The rest of the strata package matters as much: strata insurance deductibles, what a BC strata can still restrict, and for new construction, what you sign on a Langley presale.
For owners now
Ask council whether the report is done or booked. If it is not, the deadline is close. If you plan to install a charger, know that the set process applies once the report is in place or the deadline passes. From then on, a properly made request can't be unreasonably refused.
If you are buying or selling a townhouse or condo in Langley, South Surrey or White Rock, I read the strata reports with you before the subjects come off.
Sources
Province of British Columbia strata housing pages from www2.gov.bc.ca: electrical planning reports (published June 5, 2026) and electric vehicle charging (published April 24, 2025), for the deadlines, report content, qualified professionals, payment, Form B disclosure, the owner request process and vote thresholds. Strata Property Act sections 71, 82, 90.1 to 90.3, 94.1 and 96, and Strata Property Regulation Parts 5.1 and 5.2, as cited on those pages. Metro Vancouver member jurisdictions page from metrovancouver.org. Checked November 15, 2026. Not legal or electrical advice.